Title:
CONSTRUCTION OF QAISSAMANI DAM & DESIGN AND CONSTRUCTION OF THE WATER TREATMENT PLANT -VOLUME 2- LOT B
Code:
WAT/11/4
Supervisor:
COUNCIL FOR DEVELOPMENT AND RECONSTRUCTION
Author:
LIBANCONSULT AGM Ingénieurs Conseils
Page Numbers:
107
Summary:
CONDITIONS OF CONTRACT
-General
-Part I – General Conditions of Contract
-Part II – Conditions of Particular Application
-Clause 1 The Contract
-Clause 3 The Employer’s Representative
-Clause 4 The Contractor
-Clause 5 Design
-Clause 6 Staff and Labour
-Clause 8 Commencement, Delays and Suspension
-Clause 10 Employers Taking –Over
-Clause 11 Tests after Completion
-Clause 12 Defects Liability
-Clause 13 Contract Price and Payment
-Clause 15 Default of Contractor
-Clause 16 Default of Employer
-Clause 17 Risk and Responsibility
-Clause 18 Insurance
-Additional Clauses
-Annex 1 : Employer’s Requirements
Year:
2011
Sub-Sector:
Energy and water